(61) Which of the following is true about pure risk? Answer:D Answer:A Answer:A Answer:A Answer:E Answer:A Answer:E Answer:A Answer:E Answer:D Answer:D Answer:A Answer:A Answer:E Answer:C Answer:D Answer:D Answer:A Answer:D Answer: A Answer: D Answer: D Answer: B Answer: A ANSWER: C ANSWER: D ANSWER: A ANSWER: C ANSWER: A Answer: E
(62) A contingency plan is:
(63) Deflection or transfer of a risk to another party is part of which of the following risk response categories?
(64) Management reserves are used to handle which type of risk?
(65) Which of the following is considered during the Procurement Planning Process?
(66) From a buyer's standpoint, which of the following is true?
(67) Which of the following is true about procurement documents?
(68) Which of the following is a method for quantifying qualitative data in order to minimize the effect of personal prejudice on source selection?
(69) Which of the following are examples of indirect costs?
(70) Which of the following contract types places the greatest risk on the seller?
(71) In which of the following contract types is the seller's profit limited?
(72) A cost-plus-percentage-cost (CPPC. contract has an estimated cost of $120,000 with an agreed profit of 10% of the costs. The actual cost of the project is $130,000. What is the total reimbursement to the seller?
(73) A fixed-price-plus-incentive-fee (FPI. contract has a target cost of $130,000, a target profit of $15,000, a target price of $145,000, a ceiling price of $160,000, and a share ratio of 80/20. The actual cost of the project was $150,000. How much profit does the seller make?
(74) Under what circumstances is it better for a contractor to subcontract?
(75) Which type of bilateral contract is used for high dollar, standard items?
(76) In which stage of the negotiation meeting are points of concession identified?
(77) Which of the following is NOT a method of government procurement?
(78) The "rule of seven" as applied to process control charts means that :
(79) There is project with CPI of 0.81 and TCPI=1.00001 this project is:
(80) A collection of generally sequential project phases whose name and number are determined by the control needs of the organization or organizations involved in the project, is called:
(81) What does RDU stand for?
(82) Who is responsible for risk identification, risk quantification, risk response development, risk Monitor and Control?
(83) Three Point Statistical Estimating Formula Group. Expected Value =
(84) Two Point Delphi Estimate, The Best and Worst Case effort calculation:
(85) What does TQM stand for?
(86) Examples of Projects include:
(87) Projects are undertaken at all levels of the organization?
(88) 7. ________ means that every project has a definite beginning and a definite end.
(89) The smallest unit of time used in scheduling the project is known as:
(90) Who should be involved in the project planning phase?
Welcome
Blog Archive
-
▼
2010
(32)
-
▼
April
(24)
- What is a Project?
- Tips for Passing the PMP Exam
- Who are Project Stakeholders?
- PMP Certification Eligibility Requirements
- Project Management Best Practices – PMBOK 4
- One Page Formulas for PMP Exam
- Advantages of PMP Certification
- Characteristics of Project Life Cycle
- PMP Sample Questions – Part 16
- PMP Sample Questions – Part 15
- PMP Sample Questions – Part 14
- PMP Sample Questions – Part 13
- PMP Sample Questions – Part 12
- PMP Sample Questions – Part 11
- PMP Sample Questions – Part 10
- PMP Sample Questions – Part 9
- PMP Sample Questions – Part 8
- PMP Sample Questions – Part 7
- PMP Sample Questions – Part 6
- PMP Sample Questions – Part 5
- PMP Sample Questions – Part 4
- PMP Sample Questions – Part 3
- PMP Sample Questions – Part 2
- PMP Sample Questions – Part 1
-
▼
April
(24)
Labels
- ITIL Foundation (1)
- ITIL V3 (1)
- PDUs and PMI Examinations (1)
- PMBOK 4 (1)
Posted by
Sikander Baig
Wednesday, April 7, 2010
Subscribe to:
Post Comments (Atom)