(121) When you are closing out a project, what must you do? Answer: B Answer: C Answer: A Answer: D Answer: A Answer: D Answer: A Answer: D Answer: C Answer: C Answer: A Answer: D Answer: D Answer: A Answer: C Answer: A Answer: C Answer:B Answer: A Answer: D Answer: C Answer:A Answer:B Answer: C Answer:B Answer:D Answer: D Answer: D Answer: C Answer: C(151) Quality control is: Answer: B Answer: A Answer: E Answer: C Answer: D Answer: E Answer: A Answer: E Answer: C Answer: A
(122) Financial controls that need to be considered for project plan development do not include:
(123) A project manager has been working on a project for six months with the same team yet the team still shows a lack of support for the project. The best thing for the project manager to do would be to?
(124) A project has several teams. Team C has repeatedly missed several deadlines in the past causing Team D to have to crash the critical path several times. As the project leader for Team D, what should you do?
(125) The current update to the schedule performance report shows no schedule variance. Based upon the reporting, you have told the client that the project is on time. However, your team members know that a major milestone has just been missed and that the project will not meet its startup date. This is an indication of poor?
(126) A project manager is assigned a project with a team that has already been selected. The first thing the project manager should find out about the team is?
(127) An advisor to a new project manager tells the project manager to create lessons learned at the end of a project. A lessons learned includes?
(128) A project management professional can compare earned value performance data to all of the following project management tools EXCEPT:
(129) The project is completed and the final deliverable given to the customer but the customer refuses to take any action to give final acceptance on the project. The project manager should?
(130) Your new product development project has resulted in a highly successful new product. The property, equipment, materials, and personnel of your project are now being integrated into the functional organization. Your project is being terminated by:
(131) The Precedence Diagramming Method :
(132) Gantt charts are great for:
(133) Ultimate responsibility for quality management in the project rests with the?
(134) Design of experiments?
(135) You are a project manager for a major information systems project. Someone from the quality department comes to see you about beginning a quality audit of your project. The team, already under pressure to complete the project as soon as possible, takes objection to the audit. You should explain to the team that the purpose of a quality audit is?
(136) You manage a project whose team members have diverse skills and expertise. You want to encourage your staff to pool its knowledge on project issues to make the best decisions possible. The most appropriate management style to use is:
(137) The types of power that have substantial influence on both subordinates and upper management are:
(138) Your preferred resource is not available at the time needed. What is the best thing to do?
(139) An important piece of hardware will be late. What is the first thing to do?
(140) A project has experienced significant delays due to equipment problems, staff attrition, and slow client reviews. The project is 40% complete and has used 60% of the available calendar time. What is the FIRST thing you should do?
(141) A functional manager wants to make a change to the time associated with a task, but there is not enough reserve to accommodate the change. Who should authorize the change?
(142) During the course of a project you have motivated team members, managed conflict, performed personnel administrative functions and negotiated for more resources. These are examples of:
(143) You have been promoted to Manager, Continuous Process Improvement. Your new position:
(144) Which of the following is not a Project Management knowledge area?
(145) The state of being totally answerable for the satisfactory completion of a specific assignment is called:
(146) You are responsible for the communication controls for the Genesis series of satellites. Your current assignment is:
(147) Work packages are used to :
(148) Network planning methods(PERT/CPM/PDM):
(149) Earned value can be described as:
(150) A role of the change control board is to:
(152) Cost of quality is a concept that includes:
(153) The pillars) of quality is (are) :
(154) Quality assurance is:
(155) The zero defects concept:
(156) When appointed, a project manager has the inherent forms of legitimate power conveyed to him. The three forms of legitimate power are:
(157) The five types of conflict resolution are listed below and represent, in general order of importance, the methods a project manager should use to manage conflict. The one used most often by project managers to resolve conflict is:
(158) The process of getting a group of diverse individuals to work effectively together as a team is the definition of
(159) Which contract type should be used by the owner on a high risk project?
(160) PMI suggests which of the following behaviors as part of contract negotiations?
Welcome
Blog Archive
-
▼
2010
(32)
-
▼
April
(24)
- What is a Project?
- Tips for Passing the PMP Exam
- Who are Project Stakeholders?
- PMP Certification Eligibility Requirements
- Project Management Best Practices – PMBOK 4
- One Page Formulas for PMP Exam
- Advantages of PMP Certification
- Characteristics of Project Life Cycle
- PMP Sample Questions – Part 16
- PMP Sample Questions – Part 15
- PMP Sample Questions – Part 14
- PMP Sample Questions – Part 13
- PMP Sample Questions – Part 12
- PMP Sample Questions – Part 11
- PMP Sample Questions – Part 10
- PMP Sample Questions – Part 9
- PMP Sample Questions – Part 8
- PMP Sample Questions – Part 7
- PMP Sample Questions – Part 6
- PMP Sample Questions – Part 5
- PMP Sample Questions – Part 4
- PMP Sample Questions – Part 3
- PMP Sample Questions – Part 2
- PMP Sample Questions – Part 1
-
▼
April
(24)
Labels
- ITIL Foundation (1)
- ITIL V3 (1)
- PDUs and PMI Examinations (1)
- PMBOK 4 (1)
Posted by
Sikander Baig
Wednesday, April 7, 2010
Subscribe to:
Post Comments (Atom)