Which of the following is a tool used to secure expert judgment? Answer: B Based on the information provided below, which project would you recommend pursuing? Project I, with BCR (Benefit Cost ratio) of 1:1.6; Answer: B What the project manager to ensure that all work in the project is included should do? Answer: C What kind of a relationship is implied when completion of a successor is dependent on initiation of its predecessor? Answer: D What should a project manager do or follow to ensure clear boundaries for project completion? Answer: B An organization is certified to a stringent environmental standard and uses that as the key differentiator with its competitors. Alternative identification during scope planning for a particular project has thrown up an expeditious approach to achieve a project need, but this involves a risk of environmental contamination. The team evaluates that the likelihood of the risk is very low. What should the project team do? Answer: A Task Optimistic Most likely Pessimistic A 15 25 47 B 12 22 35 C 16 27 32 Answer: B Explanation: The critical path is the longest duration path through a network and determines the shortest time to complete the project. The PERT estimates of the tasks listed are 27, 22.5 & 26. Therefore, the length of the critical path of the project is 27+22.5+26 = 75.5. The standard deviations of the estimates of the three tasks are determined as (P-O)/6 = 2, 3.83 & 2.67 respectively. The standard deviation of the total path is determined as Sq. root (sum of variances), where variance = square of standard deviation. Thus, standard deviation of critical path = Sq. root (4+14.67+7.13) = 5.08. After a study of the work processes on a project, a quality audit team reports to the project manager that irrelevant quality standards were being used by the project, which might lead to rework. What was the objective of the project manager in initiating this study? Answer: D Which of the following provides the foundation for team development? Answer: D Which of the following is NOT an input to project plan execution? Answer: A A project manager would find team development the most difficult in which form of organization? Answer: A The project manager of a large multi-location software project team has 24 members, out of which 5 are assigned to testing. Due to recent recommendations by an organizational quality audit team, the project manager is convinced to add a quality professional to lead the test team at additional cost, to the project. The project manager is aware of the importance of communication, for the success of the project and takes this step of introducing additional communication channels, making it more complex, in order to assure quality levels of the project. Answer: A Once the project is complete, the complete set of project records should be put in which of the following? Answer: A Which of the following is a common format for performance reporting? Answer: B If the cost variance is positive and the schedule variance is also positive, this indicates the: Answer: A During execution of a project, an identified risk event occurs that results in additional cost and time. The project had provisions for contingency and management reserves. How should these be accounted for? Answer: A Which one of the following is the last step of project closing? Answer: B Who should be involved in the creation of lessons learned, at closure of a project? Answer: A An organization has recently started outsourcing work to a low cost, high value, engineering center located in a different country. Which of the following should the project manager provide for the team as a proactive measure? Answer: C While reviewing the progress, the project manager assesses that an activity has been missed out from the implementation plan. A milestone, scheduled to be achieved within another week, would be missed with the current implementation plan. Which of the following is the next best action for the project manager in this situation? Answer: D Which of the following it the logical flow of any project? Answer: D In which phase of a project would you estimate activity duration and resources? Answer: C Which of the following according to the PMBOK is described as, "a category or rank given to entities having the same functional use but different technical characteristics?" Answer: A Which of the following is another name for an Ishikawa diagram? Answer: A Refinements are considered updates for the ____. Answer: C The acronym CPPC stands for? Answer: A Which of the following is not considered part of Maslow's Hierarchy of Needs? Answer: C Parento diagrams work on the ___ rule. Answer: C Which of the following is a key aspect of quality control? Answer: D The creator of the project charter is identified as the ______. Answer: B You are managing the release of a new drug in the market. Your role is that of a: Answer: B Which of the following is not the feature of a project? Answer: D You are managing the release of a new drug in the market. Your role is that of a: Answer: B Which of the following statement related to Standards and Regulations is not correct? Answer: D Your IT company is responsible for making software virus programs. You are responsible for managing both the individual product releases and the co-ordination of multiple releases over time. Your role is that of a: Answer: A A Project Manager must have good understanding of the mechanics of power and politics to be effective. As defined by Pfeffer, power includes all the following except: Answer: D Which of the following statement related to Standards and Regulations is not correct? Answer: D A Project Manager must have good understanding of the mechanics of power and politics to be effective. As defined by Pfeffer, power includes all the following except: Answer: D Phase end review of projects is also referred to as: Answer: D You are working in the Project Office of your organization. What is your job responsibility? answer: C
Explanation: The 'Delphi technique' is a commonly used tool to secure expert judgment while initiating a project.
'Peer review' is a project selection tool, 'Expected value' is a method quantitative risk analysis, and 'WBS' is a project-planning tool.
Project II, with NPV of US $ 500,000;
Project III, with IRR (Internal rate of return) of 15%
Project IV, with opportunity cost of US $ 500,000.
Explanation: Project III has an IRR of 15%, which means the revenues from the project equal the cost expended at an interest rate of 15%.
This is a definitive and a favorable parameter, and hence can be recommended for selection.
Project I have an unfavorable BCR and hence cannot be recommended.
Information provided on projects II and IV is not definitive, and hence neither of projects II and IV qualifies for a positive recommendation.
Explanation: A WBS is a deliverable oriented grouping of project components that organizes and defines the total scope of the project.
Explanation: A start-to-finish (SF) relationship between two activities implies that the completion of successor is dependent on the initiation of its predecessor.
A finish-to-start (FS) relationship between two activities implies that the initiation of successor is dependent on the completion of predecessor.
A finish-to-finish (FF) relationship between two activities implies that the completion of successor is dependent on the completion of predecessor.
A start-to-start (SS) relationship implies that the initiation of successor is dependent on the initiation of predecessor..
Explanation: The project team must complete a scope statement for developing a common understanding of the project scope among stakeholders. This lists project deliverables - summary level sub-products, whose full and satisfactory delivery marks the completion of the project.
Scope verification is the process of securing a formal acceptance of the project scope by stakeholders.
Scope definition is the process of subdividing the major project deliverables into smaller, more manageable components.
A risk management plan involves setting up processes for identifying and dealing with project risks.
Explanation: The organization's reputation being at stake, the threshold for such a risk would be very low.
Mitigation plan against an environmental contamination would mean reducing the impact, which may not be a plausible response.
Procuring an insurance against the risk would only transfer the monetary impact of the risk, and not the intangible impact like, the reputation of the organization.
Planning precautions against the occurrence would still leave an opportunity of occurrence.
This cannot be completely avoided.
The best option would be to drop the approach - that is, complete avoidance of the risk.
Explanation: Determining validity of quality standards, followed by the project is a 'quality assurance' activity.
Compliance of work results to required specifications is a 'quality control' activity.
Determining quality standards is a 'quality planning' activity.
'Checking adherence to processes' is a quality audit activity to ensure that standard operating procedures or job instruction documents (SOPs or JIDs) are being followed for producing the deliverables of the process.
Explanation: Individual development (managerial and technical) is the foundation of a team.
Explanation: In a functional organization, the project team members have dual reporting to two bosses - the project manager and the functional manager.
In a weak matrix organization, the power rests with the functional manager.
In a balanced matrix organization, the power is shared between the functional manager and the project manager. A projectized organization is grouped by projects and the project manager has complete control on the project and its team.
A Tight matrix organization refers to co-locating the project team and has nothing to do with a matrix organization.
Therefore, a project manager would find it difficult to drive team development in a weak matrix organization.
How many additional communication channels are introduced as a result of this organizational change in the project?
Explanation: Number of communication channels with "n" members = n*(n-1)/2
Originally the project has 25 members (including the project manager), which makes the total communication channels as 25*24/2 = 300.
With the addition of the quality professional as a member of the project team, the communication channels increase to 26*25/2 = 325.
Therefore, the additional channels as a result of the change, that is, 325-300 = 25.
Explanation: Project records should be prepared for archiving by the appropriate parties.
Explanation: Common formats for Performance Reports are, bar charts (also called Gantt Charts), S-curves, histograms and tables etc.
Explanation: Positive Schedule Variance means the project is ahead of schedule; Negative Cost Variance means the project is over-budget.
Explanation: The question is about correct accounting for risk events that occur and updating the reserves.
Reserves are meant for making provisions in cost and schedule, to accommodate for consequences of risk events.
Risk events are classified as "unknown unknowns" or "known unknowns", where "unknown unknowns" are risks that were are not identified and accounted for, while "known unknowns" are risks that were identified and provisions were made for them.
Provisions for "unknown unknowns" are in management reserves while those for "known unknowns" are accommodated in contingency reserves. Management reserves are at the discretion of senior management while the contingency reserves are at the project manager's discretion.
Residual and secondary risks are remaining unmitigated risks and resultant risks of mitigation, respectively. These are not reserves.
In this case, the risk event is one of the identified risks and therefore, 'contingency reserve' is the one where the cost and schedule impact would be accommodated in.
Explanation: Archiving is the last step in the project closing.
Explanation: 'Stakeholders' include everyone who are actively involved in the project or whose interests may be affected as a result of the project execution or completion.
The 'project team' creates the lessons learned on the project.
The role of the 'project office' depends on the function defined for it within the performing organization and it could be either facilitating best practices for all projects or could constitute the project team.
As lessons learned should capture all variations and what could have been done better for future deployment, 'stakeholders' should be involved in creation of lessons learned.
Explanation: Understanding cultural differences is the first step towards an effective communication amongst the project team involving outsourced work from a different country. So, what is needed in this case is 'an exposure to the cultural differences', which is being mentioned as choice C.
Choice A, that is, 'a training course on the laws of the country' is a subject of legal experts and not of the project team.
Choice B, that is, ' a course on linguistic differences' would not serve the purpose of understanding and appreciating cultural differences, for better teaming.
Choice D, that is, 'a communication management plan' is a document that provides data gathering and dissemination amongst stakeholders of the project. It is necessary for the project but does not help in bridging communication gaps across different cultures
Explanation: Choice D, that is, 'assess alternatives to meet the milestone' indicates confronting the issue with an attempt to resolve the issue. Hence this would be the best approach.
Choices A and C, that is, 'report the error and the expected delay' or 'report the error and the planned recovery actions' do not attempt to solve the problem.
An attempt to solve the problem is the next best thing to do in this situation, before reporting the issue correctly.
Choice B, that is, 'omit the status update on the milestone' is unethical.
Explanation: Projects involve doing something that has not been done before and which is, therefore, unique. A product or service may be unique even if the category to which it belongs is large....
A project to bring a new drug to market may require thousands of doses of he drug to support clinical trials
Explanation: Operations and projects differ primarily in that operations are ongoing and repetitive while projects are temporary and unique. A project can thus be defined in terms of its distinctive characteristics - a project is a temporary endeavor undertaken to create a unique product or service
Explanation: Projects involve doing something that has not been done before and which is, therefore, unique. A product or service may be unique even if the category to which it belongs is large.
A project to bring a new drug to market may require thousands of doses of he drug to support clinical trials.
Explanation: For many projects, standards and regulations (by whatever definition) are well known and project plans can reflect their effects. In other cases, the influence is unknown or uncertain and must be considered under Project Risk Management
Explanation: A program is a group of projects managed in a co-ordinated way to obtain benefits which are not available from managing them individually. Many programs also involve elements of ongoing operations.
Explanation: Pfeffer defines power as "the potential ability to influence behavior, to change the course of events, to overcome resistance, and to get people to do things that they would not otherwise do."…The negative sense, of course derives from the fact that attempts to reconcile these interests result in power struggles and organizational games that can sometimes take on a thoroughly unproductive life of their own.
Explanation: For many projects, standards and regulations (by whatever definition) are well known and project plans can reflect their effects. In other cases, the influence is unknown or uncertain and must be considered under Project Risk Management.
Explanation: Pfeffer defines power as "the potential ability to influence behavior, to change the course of events, to overcome resistance, and to get people to do things that they would not otherwise do."…The negative sense, of course derives from the fact that attempts to reconcile these interests result in power struggles and organizational games that can sometimes take on a thoroughly unproductive life of their own.
Explanation: The conclusion of a project phase is generally marked by a review of both key deliverables and project performance to date, to a) determine if the project should continue into its next phase and b) detect and correct errors cost effectively. These phase-end reviews are after called phase exits, stage gates or kill points
Explanation: Project Office: There is a range of uses for what constitutes a project office. A project office may operate on a continuum from providing support functions to project managers in the form of training, templates, etc. to actually being responsible for the results of the project
Welcome
Blog Archive
-
▼
2010
(32)
-
▼
April
(24)
- What is a Project?
- Tips for Passing the PMP Exam
- Who are Project Stakeholders?
- PMP Certification Eligibility Requirements
- Project Management Best Practices – PMBOK 4
- One Page Formulas for PMP Exam
- Advantages of PMP Certification
- Characteristics of Project Life Cycle
- PMP Sample Questions – Part 16
- PMP Sample Questions – Part 15
- PMP Sample Questions – Part 14
- PMP Sample Questions – Part 13
- PMP Sample Questions – Part 12
- PMP Sample Questions – Part 11
- PMP Sample Questions – Part 10
- PMP Sample Questions – Part 9
- PMP Sample Questions – Part 8
- PMP Sample Questions – Part 7
- PMP Sample Questions – Part 6
- PMP Sample Questions – Part 5
- PMP Sample Questions – Part 4
- PMP Sample Questions – Part 3
- PMP Sample Questions – Part 2
- PMP Sample Questions – Part 1
-
▼
April
(24)
Labels
- ITIL Foundation (1)
- ITIL V3 (1)
- PDUs and PMI Examinations (1)
- PMBOK 4 (1)
Posted by
Sikander Baig
Tuesday, April 6, 2010
Subscribe to:
Post Comments (Atom)