The _________ is a time-phased budget that will be used to measure and monitor cost performance in the project. Answer: C To transfer most of the cost risk to the contractor, the client may use a ___________ contract. Answer: D An appropriate sequence for risk management activities is: Answer: A Theory X holds that: Answer: D All of the following are characteristics of parametric estimating except: Answer: D Inputs to cost budgeting include all of the following except: Answer: A Inputs used during scope planning include all of the following except: Answer: C Cost control outputs include all of the following except: Answer: D Risk identification outputs include the following except: Answer: A Inputs into overall change control include all of the following except: Answer: C At XYZ InC., the hourly wage for semi-skilled workers is $14.00. The annual audit shows that fringe benefits cost 30% of basic wages, and that overhead costs are 60% of wages plus fringe benefits. What is the "loaded" hourly wage for a semi-skilled worker at XYZ Inc.? Answer: D Of the following estimates, which most accurately reflect the actual cost of the project? Answer: D The most crucial time for project risk assessment is: Answer: B When there is uncertainty associated with one or more aspects of the project, one of the first steps to take is to: Answer: B Including a contingency reserve in the project budget is intended to: Answer: C Given the information in the following table, what is the expected value from this risk event? Probability Result Answer: D A contractor is working on a fixed price contract that calls for a single, lump sum payment upon satisfactory completion of the contract. About halfway through the contract, the contractor's project manager informs their contract administrator that financial problems are making it difficult for them to pay their employees and subcontractors. The contractor asks for a partial payment for work accomplished. Which of the following actions by the buyer is most likely to cause problems for the project? Answer: B A precise description of a physical item, procedure, or service for implementation of an item or service is called a: Answer: C A project should be terminated for all of the following reasons except: Answer: A One common way to compute estimated at completion (EAC) is to take the project budgeted-at-completion and: Answer: D
.4 -10,000
.3 -7,500
.2 -5,000
.1 +2,500
Welcome
Blog Archive
-
▼
2010
(32)
-
▼
April
(24)
- What is a Project?
- Tips for Passing the PMP Exam
- Who are Project Stakeholders?
- PMP Certification Eligibility Requirements
- Project Management Best Practices – PMBOK 4
- One Page Formulas for PMP Exam
- Advantages of PMP Certification
- Characteristics of Project Life Cycle
- PMP Sample Questions – Part 16
- PMP Sample Questions – Part 15
- PMP Sample Questions – Part 14
- PMP Sample Questions – Part 13
- PMP Sample Questions – Part 12
- PMP Sample Questions – Part 11
- PMP Sample Questions – Part 10
- PMP Sample Questions – Part 9
- PMP Sample Questions – Part 8
- PMP Sample Questions – Part 7
- PMP Sample Questions – Part 6
- PMP Sample Questions – Part 5
- PMP Sample Questions – Part 4
- PMP Sample Questions – Part 3
- PMP Sample Questions – Part 2
- PMP Sample Questions – Part 1
-
▼
April
(24)
Labels
- ITIL Foundation (1)
- ITIL V3 (1)
- PDUs and PMI Examinations (1)
- PMBOK 4 (1)
Posted by
Sikander Baig
Tuesday, April 6, 2010
Subscribe to:
Post Comments (Atom)