(31) Which of the following is not an external-unpredictable risk? Answer:D Answer:C Answer:C Answer:C Answer:D Answer:C Answer:C Answer:D Answer:C Answer:A Answer:D Answer:D Answer:A Answer:A Answer:C Answer:B Answer:B Answer:D Answer:B Answer:A(51) All of the following are communication tools EXCEPT: Answer:E Answer:D Answer:B Answer:C Answer:C Answer:D Answer: B Answer:C Answer:E Answer:C
(32) Maslow ranked Human needs from the highest to lowest:
(33) Which of the following statements concerning contract type is correct?
(34) Herzberg identified factors, which, if present, will lead to increased motivation. A typical factor would be:
(35) Your customer ask for a small change in the project, which was not budgeted in the project. It is a small effort as compared to the total project and you need the goodwill for a multimillion dollar on the pipeline. You will
(36) You are responsible for ensuring that your seller's performance meets contractual requirements. For effective contract administration, you should:
(37) The three major causes of change on a project are:
(38) The purpose of the review of deliverables and project performance at the conclusion of a project phase is to:
(39) Your project is in the final test stage, the user acceptance test. It meets all the product specs and is under planned costs. In term of schedule, this project is ahead. Your customer meet you and requested that he will not accept the product unless you make several changes. What you should do is:
(40) The delphi Method is best suited for:
(41) Which of the following methods is least likely to be used for explaining project planning guidelines to the team?
(42) Projects are initiated in response of:
(43) The party that needs the change resulting from the project, and who will be its custodian on completion is the:
(44) A document or tool which describes when and how human resources will be brought onto and taken off the project team is called a:
(45) In which type of organization is team building likely to be most difficult?
(46) A tool which links the project roles and responsibilities to the project scope definition is called:
(47) Which of the following are outputs from the Communications Planning process?
(48) The receiver filters messages based on all but the following:
(49) The sending or conveying of information from one place to another is the process of:
(50) The three major types of communication are:
(52) Communication is the PRIME responsibility of a Project:
(53) What are the four parts of the communications model?
(54) In negotiating with functional department managers, project managers often find themselves using what two-party conflict management approach?
(55) A leadership style in which the project manager shares problems with team members and formulates solutions as a group is called:
(56) A type of organization in which the project manager has little formal authority and basically acts as a staff assistant to an executive who is ultimately responsible for the project is called:
(57) Create WBS process belongs to:
(58) In which of the following organizations is the project manager role likely to be part-time?
(59) Project Risk Management includes all of the following processes except:
(60) Using the PMBOK definition of contingency reserve, which of the following statements about contingency reserves is false?
Welcome
Blog Archive
-
▼
2010
(32)
-
▼
April
(24)
- What is a Project?
- Tips for Passing the PMP Exam
- Who are Project Stakeholders?
- PMP Certification Eligibility Requirements
- Project Management Best Practices – PMBOK 4
- One Page Formulas for PMP Exam
- Advantages of PMP Certification
- Characteristics of Project Life Cycle
- PMP Sample Questions – Part 16
- PMP Sample Questions – Part 15
- PMP Sample Questions – Part 14
- PMP Sample Questions – Part 13
- PMP Sample Questions – Part 12
- PMP Sample Questions – Part 11
- PMP Sample Questions – Part 10
- PMP Sample Questions – Part 9
- PMP Sample Questions – Part 8
- PMP Sample Questions – Part 7
- PMP Sample Questions – Part 6
- PMP Sample Questions – Part 5
- PMP Sample Questions – Part 4
- PMP Sample Questions – Part 3
- PMP Sample Questions – Part 2
- PMP Sample Questions – Part 1
-
▼
April
(24)
Labels
- ITIL Foundation (1)
- ITIL V3 (1)
- PDUs and PMI Examinations (1)
- PMBOK 4 (1)
Posted by
Sikander Baig
Wednesday, April 7, 2010
Subscribe to:
Post Comments (Atom)