(161) Project risk is characterized by three factors: Answer: C Answer: D Answer: C Answer: B Answer: C Answer: A Answer: C Answer: A Answer: B Answer: B Answer: B Answer: B Answer: C Answer: B Answer: C Answer: A Answer: C Answer: D Answer: E Answer: B Answer: E Answer: D Answer: A Answer: A Answer: E Answer: E Answer: D Answer: A Answer: B Answer: D Answer: E Answer: A Answer: B Answer: E Answer: B Answer: C Answer: E Answer: D Answer: C Answer: E
(162) Name the ethical code you'll be required to adhere to as a PMP:
(163) Which is not another term for contract?
(164) Which of the following situations describes a violation of the PMP. Professional Code of Conduct?
(165) You are working in a country where it is customary to exchange gifts between contractor and customer. Your company code of conduct clearly states that you cannot accept gifts from any client. Failure to accept the gift from this client may result in termination of the contract. The action to take in this case would be:
(166) An example of a conflict of interest would be:
(167) Your project is running out of cash and significant work remains. You are directed by senior management to instruct your people to use another project's charge numbers while working on your project. You should:
(168) Project Managers can contribute to their organization's knowledge base and to the profession of project management most effectively by:
(169) For a festival, you give your government client a leather brief case. You are in violation of the responsibility to:
(170) You have just changed jobs and discovered that your new employer routinely violates OSHA/EPA and affirmative action requirements on projects. You should:
(171) During your assignment as project manager you add a new member to your project team. This new team member was recently hired from a competitor and offers to share a substantial amount of proprietary information from his previous company. This information could put you and your team in a very strong position for future business. You are aware of a non-compete clause in the new hire's condition of employment. You should:
(172) Before reporting a perceived violation of an established rule or policy the project manager should:
(173) A response to a negative risk event is known as a:
(174) Qualitative Risk Analysis will be performed under :
(175) Acquire Project team process will be performed under:
(176) The terms "Facilitating Processes" and "Core Processes" are no longer used in new PMBOK. These terms have been eliminated to ensure that all project management processes in the Project Management Process Groups have the same level of importance.
(177) In a group of 4 members, 1 member has been added. How many communication channels are there now :
(178) Which statement is correct :
(179) Which of the following is not an input to Develop Project Charter:
(180) Which of the following is a tool used to Create WBS:
(181) Which of the following is not an input to Activity Definition process:
(182 ) Which of the following is not an output of Activity Resource Estimating:
(183) Which of the following is a tool used in Activity Duration Estimating:
(184) Crashing, and Fast tracking are techniques used in the following process:
(185) Which is not a technique used for cost estimation :
(186) Which is not a tool used in Quality Planning process :
(187) What are three tools used in Quality Control Process:
(188) Which of the following Human Resource process generates Roles & Responsibilities :
(189) Co-Location is a techniques which means:
(190) Manage Stakeholders is a part which of the following process group:
(191) Which is not correct about Communications Management Plan document:
(192) Which is not a tool used for Risk Response Planning:
(193) Advertising is a technique used in which of the following process:
(194) Which of the following definition is not correct:
(195) Which of the following definition is not correct:
(196) Which of the following is not correct:
(197) Which of the following is not correct :
(198) Most schedule simulations are based on some form of which of the following?
(199) What is critical path?
(200) In the communication process, "noise" is the word used to describe factors and forces inhibiting the exchange of information between two or more parties. Noise includes all of the following but __________
Welcome
Blog Archive
-
▼
2010
(32)
-
▼
April
(24)
- What is a Project?
- Tips for Passing the PMP Exam
- Who are Project Stakeholders?
- PMP Certification Eligibility Requirements
- Project Management Best Practices – PMBOK 4
- One Page Formulas for PMP Exam
- Advantages of PMP Certification
- Characteristics of Project Life Cycle
- PMP Sample Questions – Part 16
- PMP Sample Questions – Part 15
- PMP Sample Questions – Part 14
- PMP Sample Questions – Part 13
- PMP Sample Questions – Part 12
- PMP Sample Questions – Part 11
- PMP Sample Questions – Part 10
- PMP Sample Questions – Part 9
- PMP Sample Questions – Part 8
- PMP Sample Questions – Part 7
- PMP Sample Questions – Part 6
- PMP Sample Questions – Part 5
- PMP Sample Questions – Part 4
- PMP Sample Questions – Part 3
- PMP Sample Questions – Part 2
- PMP Sample Questions – Part 1
-
▼
April
(24)
Labels
- ITIL Foundation (1)
- ITIL V3 (1)
- PDUs and PMI Examinations (1)
- PMBOK 4 (1)
Posted by
Sikander Baig
Wednesday, April 7, 2010
Subscribe to:
Post Comments (Atom)