(61) Which of the following is true about pure risk?
- The risk can be deflected or transferred to another party through a contract or insurance policy.
- Pure risks involve the chance of both a profit and a loss.
- No opportunities are associated with pure risk, only losses.
- a and c
- a and b
Answer:D
(62) A contingency plan is:
- A planned response that defines the steps to be taken if an identified risk event should occur.
- A workaround
- A reserve used to allow for future situations which may be planned for only in part.
- a and c
- a and b
Answer:A
(63) Deflection or transfer of a risk to another party is part of which of the following risk response categories?
- Mitigation
- Acceptance
- Avoidance
- Analysis
Answer:A
(64) Management reserves are used to handle which type of risk?
- Unknown unknowns
- Known unknowns
- business risks
- pure risks
Answer:A
(65) Which of the following is considered during the Procurement Planning Process?
- Whether to procure
- How to procure and how much to procure
- What and when to procure
- b and c
- all of the above
Answer:E
(66) From a buyer's standpoint, which of the following is true?
- Procurement planning should include consideration of potential subcontracts
- Procurement planning does not include consideration of potential subcontracts since this is the duty of the contractor.
- Subcontractors are first considered during the Solicitation Process
- none of the above
Answer:A
(67) Which of the following is true about procurement documents?
- Procurement documents are used to solicit proposals from prospective sellers.
- Invitation for Bid and Request for Proposal are two examples of procurement documents.
- Procurement documents should be structured to facilitate accurate and complete responses from prospective sellers.
- b and c
- all of the above
Answer:E
(68) Which of the following is a method for quantifying qualitative data in order to minimize the effect of personal prejudice on source selection?
- Weighting system
- Screening system
- Selecting system
- none of the above
- all of the above
Answer:A
(69) Which of the following are examples of indirect costs?
- Salaries of corporate executives
- Salaries of full-time project staff
- Overhead costs
- a and b
- a and c
Answer:E
(70) Which of the following contract types places the greatest risk on the seller?
- Cost-plus-fixed-fee contract
- Cost plus-incentive-fee contract
- Fixed-price-incentive contract
- Firm-fixed-price contract
Answer:D
(71) In which of the following contract types is the seller's profit limited?
- Cost-plus-percentage-cost contract
- Cost-plus-fixed-fee contract
- Fixed-price-plus-incentive
- b and c
- none of the above
Answer:D
(72) A cost-plus-percentage-cost (CPPC. contract has an estimated cost of $120,000 with an agreed profit of 10% of the costs. The actual cost of the project is $130,000. What is the total reimbursement to the seller?
- $143,000
- $142,000
- $140,000
- $132,000
Answer:A
(73) A fixed-price-plus-incentive-fee (FPI. contract has a target cost of $130,000, a target profit of $15,000, a target price of $145,000, a ceiling price of $160,000, and a share ratio of 80/20. The actual cost of the project was $150,000. How much profit does the seller make?
- $10,000
- $15,000
- $0
- $5,000
Answer:A
(74) Under what circumstances is it better for a contractor to subcontract?
- The subcontractor possesses special technical and engineering skills that the contractor does not have.
- The work to be subcontracted represents almost all of the overall work effort.
- The subcontractor can perform the work at a lower cost than the contractor.
- all the above
- a and c
Answer:E
(75) Which type of bilateral contract is used for high dollar, standard items?
- Purchase order
- Request for proposal (RFP.
- Invitation for bid (IFB.
- Request for quotation (RFQ.
- all of them are appropriate
Answer:C
(76) In which stage of the negotiation meeting are points of concession identified?
- Probing
- Closure
- Agreement
- Scratch bargaining
Answer:D
(77) Which of the following is NOT a method of government procurement?
- Assistance
- Sealed Bidding
- Competitive proposals
- Acquisition
- Small purchases
- No answer provided
Answer:D
(78) The "rule of seven" as applied to process control charts means that :
- If there are seven points on one side of mean, then an assignable cause must be found.
- Seven consecutive points are ascending, descending, or the same.
- At least seven inspectors should be in place for every thousand employees.
- A process is not out of control even though seven measurements fall outside the lower and upper control limits.
Answer:A
(79) There is project with CPI of 0.81 and TCPI=1.00001 this project is:
- Overbudget and cannot recover
- Underbudget
- Overbudget and early in its evolution
- No interference cam be made
Answer:D
(80) A collection of generally sequential project phases whose name and number are determined by the control needs of the organization or organizations involved in the project, is called:
- Project life cycle
- Product life cycle
- Project life event
- All of the above
Answer: A
(81) What does RDU stand for?
- Really Dumb User
- Ready for Download Use
- Remaining Duration unassisted
- Remaining Duration
Answer: D
(82) Who is responsible for risk identification, risk quantification, risk response development, risk Monitor and Control?
- Project Communications Management
- Project human resource Management
- Project Procurement Management
- Project Risk Management
Answer: D
(83) Three Point Statistical Estimating Formula Group. Expected Value =
- (Optimistic + (4 X Most Likely) + Pessimistic ) x 6
- (Optimistic + (4 X Most Likely) + Pessimistic ) divided by 6
- (Optimistic + (4 X Most Likely) x Pessimistic ) divided by 6
- (Optimistic + (4 + Most Likely) + Pessimistic ) divided by 6
Answer: B
(84) Two Point Delphi Estimate, The Best and Worst Case effort calculation:
- Calculate (Best + Worst) / 2
- Calculate (Best +2 ) / Worst
- Calculate (2 + Worst) / Best
- none of the above
Answer: A
(85) What does TQM stand for?
- Time Quality Managed
- Target Quality Management
- Total Quality Management
- Time Quote Management
ANSWER: C
(86) Examples of Projects include:
- Implementing a new business procedure or process
- Constructing a building or facility
- Designing a new transportation vehicle
- All of the Above
ANSWER: D
(87) Projects are undertaken at all levels of the organization?
- True
- False
- Both True and False
- Neither true nor false
ANSWER: A
(88) 7. ________ means that every project has a definite beginning and a definite end.
- Overall
- Project Chart
- Temporary
- Duration
ANSWER: C
(89) The smallest unit of time used in scheduling the project is known as:
- Calendar Unit
- Scope unit
- Time Measurement
- All of the Above
ANSWER: A
(90) Who should be involved in the project planning phase?
- The Project Manager.
- The customer.
- The Sub-contractors/vendors.
- The project team members.
- All of the above.
Answer: E